This project is part of Maynilad project on the Water Discharge Pipelines from the New Pasay Pumping Station and Reservoir at PAGCOR entertainment complex.
Read More...This was a pipeline project of Maynilad along Alabang-Zapote Road in Las Piñas City. This project was secured by DMCI, and MCT was the subcontractor for the pipe-jacking portion. The steel casing was originally 1400mm Ø, but DMCI ordered to change it to 2100mm Ø.
Read More...This is a portion of the Maynilad project that is to supply water to the New Pasay Pumping Station and Reservoir newly built at PAGCOR entertainment complex. Using 2100mm Ø steel casing, the line installed crossed Roxas Blvd. towards the reservoir.
Read More...This is a project secured from a Japanese company, HRD (S) PTE. LTD. Located in the Cavite Eco-Zone, the contract was to install 900mm Ø steel pipe by pipe jacking under the existing reinforced concrete box culvert for their drainage system.
Read More...© microtunnelling.com.ph, 2018